2025 - 2026 Beach Renourishment Maps

Pending final approvals, the preliminary schedule has been updated. The following timeline may be subject to change depending on external factors beyond the Town's control.

  • Phase 1 - The Heel, Port Royal, Fish Haul and Pine Island - (August 2025 - December 2025)
  • Phase 2 - Central Island, South Island, and South Beach - (December 2025 - May 2026)
  • Phase 3 - Pine Island Structures - (TBD)

* Timeframes are subject to change

Project Timeline Map

Map of Hilton Head Island with lines and dates showing construction areas

Download the Project Timeline Map

Project Fill Placement Areas

Map of Hilton Head Island with lines showing fill areas on coastline